Develop a collaborative regional policy on redevelopment that inspires inter-jurisdictional partnerships, economically
competitive standards, and clarity among all stakeholders.

Market Measures

Number of Development/Redevelopment Projects Incorporating Urban Design Guidelines
Number of Collaborative Redevelopment Initiatives
Dollar Increase in Taxable Values in Redevelopment Areas

Action

Performance Measure

Baseline

Target

Date

Third Qtr FY 2006

Projected Cost

Objective 1: Adopt changes to existing plans and land development regulations.

Establish transit-oriented and mixed-use land use categories in the Broward County Land Use Plan.

# of Changes
in Land Development Regulations Adopted

0

3

1/1/06

N/A

Resources Allocated

Complete additional municipal demonstration plans to implement the Broward County Countywide Community Design Guidebook.

# of Demonstration Plans Completed

3

7

9/30/06

0

Resources Allocated

Develop Post-Disaster Redevelopment Ordinance for Broward County.

% of Post-Disaster Redevelopment Plan Completed

0

100%

9/30/07

0

Resources Allocated

Amend the Broward County Land Development Code and prepare model municipal code to further the recommendations of the Broward County Countywide Community Design Guidebook.

% of Code Amendments and Model Municipal Code Completed

0

100%

9/30/08

0

Resources Allocated

Amend Broward County's land development regulations to expand requirements for transit-supportive infrastructure.

% of Redevelopment Projects Along Transit Corridors with Transit-Supportive Infrastructure

0

75%

9/30/10

0

TBD

Finalize 10-year Water Supply Plan.

Adopted 10-Year Water Supply Plan

1990-2010 Plan

Adopted 10-Year Water Supply Plan

FY 2005-15
Ongoing

0

Resources Allocated

Objective 2: Implement County's redevelopment programs, projects, and initiatives.

Complete the public/private partnership feasibility study for the Downtown Campus project.

% of Study Completed

0

100%

1/1/07

85%

Resources Allocated

Prepare Request for Qualification (RFQ) for the Downtown Campus project.

RFQ Issued

0

RFQ issued

9/30/07

0

Resources Allocated

Prepare Request for Proposal (RFP) for the Downtown Campus project.

RFP Issued

0

Selection of developer for construction of Downtown Campus

9/30/08

0

Resources Allocated

Implement the Redevelopment Capital Program.

# of Interlocal Agreements (ILAs) With Municipalities and Community Redevelopment Agencies

3

6

12/31/08

1

Resources Allocated

Objective 3: Combine/collocate public facilities where feasible and appropriate. 

Plan a joint study with the School Board and municipalities.

% of Study Completed

0

100%

12/31/07

0

Resources Allocated

Objective 4: Collaborate with municipalities and other stakeholders to establish regional redevelopment policies, create effective partnerships, and develop tools to assist implementation.

Explore feasibility of acquiring sites with water access in support of the marine industry and marine recreational facilities.

% of Feasibility Analyses, Including Associated Costs and Funding Mechanisms Completed

0

100%

9/30/07

0

Resources Allocated