Current Activities

Construction Activities from November 28 - December 3 and

December 5 - 10

Contractors will perform the following work:
    




Click on the image for a larger version.
View and/or print a larger Work Area Map (PDF).

Terminal 4 (Area 4)

  • Placing concrete for the eastern phase concourse level.
  • Demolition work for the new Customs procession area.  
  • Installing the utilities, electrical, and communications for the new Customs processing area.
  • Installing the foundations for the terminal's eastern phase and the Customs processing area.
  • Installing a bag-recheck counter and handling system.
  • Installing apron drainage.
  • Installing the roof on the eastern phase concourse level.
  • Removing the carpet and installing terrazzo floors in the Baggage Claim area and by the ticket counters.

 Terminal 1 (Area 1)

  • Utility work.
  • Installing columns and pouring concrete slabs.
  • Placing concrete for the concourse level.
  • Installing the steel roof structure.
  • Installing the outer walls.

Terminal 3 (Area 3)

  • Installing a baggage conveyor system.

Pedestrian Bridges

  • Installing the steel roof structure, flooring, and lighting.
  • Repairing the steel structure.
  • Refurbishing the terminal vestibule entrances to the bridges. 
  • Demo work on the garage vestibule canopies.

 