Current Activities

Construction Activities from June 29 - July 3 and July 6 - 11

Contractors will perform the following work:


    


Click on the image for a larger version.
View and/or print a larger Work Area Map (PDF).

Crossfield Taxiways (Areas 3, 4, and 5)

  • Demolishing and recycling the old taxiway pavement.  
  • Installing drainage, utilities, and lighting.
  • Grading the ground.
  • Placing the base layer and the final top layer of concrete.


Terminal 4 Building and Apron (Area 6)

  • Installing the dry wall, electrical, fire protection, and plumbing. 
  • Painting the dry walls.
  • Installing the tile, fixtures and lighting in the bathrooms.
  • Installing the carpeting, counters, and seating by the gates.

Terminal 3 (Area 9)

  • Completing the terrazzo floor by the ticket counters and security check point for Concourse E.  

Covered Walkways (Area 10)

  • Installing the covered walkways between Terminals 1 and 2 and Terminals 3 and 4.

 

Look at a larger version of the Construction Area Map (PDF).