Eastern Runway 3
Click images for larger view
Eastern view of the South Runway under construction October 2013 - Workers prepare the eastern end of the runway for paving by removing the extra fill. The extra fill increased the rate of settling.
November 2013 eastern view of runway under construction November 2013 - Work has begun on the holding pad at the end of the runway.
Aerial photo taken in early December 2013 December 2013 - Some of the retaining wall's top cap is in place.
Eastern view taken in early January 2014 January 2014 - Most of the cap is in place. Final irrigation work next to the wall begins.
February 2014 Eastern end of South Runway February 2014 - Workers completing the cap of the wall.
View of the eastern end of the South Runway taken in March 2014 March 2014 - Near the end wall is the localizer a navigational aide.
April 2014 eastern view of the South Runway April 2014 - The limestone base layer is finished as is the yellow fall protection system around the edges of the wall.
May 2014 eastern view of the South Runway May 2014 - The asphalt base layer is placed for the Engineered Material Arresting System and the sod laid. Crews have also poured the  cement base west of the asphalt. 
June 2014 east end of the south runway June 2014 - Work underway for the exit ramp to US 1 southbound (on the left side of the photo).
July 2014 view of the eastern section of the South Runway July 2014 - The sod was placed and all the runway paving complete. Work on the taxiway is ongoing.
​​