Eastern Runway 4
August 2014 view of the eastern end of the South Runway August 2014 - The EMAS and runway are complete. Crews installing the parallel taxiway.

Click on an image for a larger view.
September 2014 eastern view of the South Runway September 2014 - Work continues on the taxiway east and west of the structures.
   October 2014 - Crews have installed the base layer of the taxiway.
 Novermber 2014 eastern view November 2014 - The parallel taxiway is completed. This view is looking east towards the ocean.
   December 2014 - The runway and taxiway construction is complete.