Official Site of FLL — Broward County, Florida  
Skip navigation links
About FLLair
Business
Program Updates
Environmental
History
Gallery
Skip navigation links
Runway Webcam
Expansion Video
Runway Animation
Terminal 4 Animation
Eastern Runway 1
Eastern Runway 2
Eastern Runway 3
Tunnels 1
Tunnels 2
Tunnels 3
Western Runway 1
Western Runway 2
Western Runway 3
Runway 1
Runway 2
Runway 3
Terminal 4 - 1
Terminal 4 - 2
Terminal 4 - 3
Western Runway 1
Western area of the South Runway
July 2012 - Western most area of the South Runway before construction began. This view is looking east.
August 2012 west view of the South Runway under construction
August 2012 - Workers started by removing the grass sod and the asphalt. This view is looking east.

Click on an image for a larger version.

Section of the South Runway next to the Diagonal Runway
September 2012 - This section of the runway is next to the Diagonal Runway that is still operational. Workers removed the asphalt. View looking east. 
South Runway under construction looking west
October 2012 - View looking west with the operational Diagonal Runway on the right of the photo.

South Runway under construction in November 2012
November 2012 - A long pile of darker crushed asphalt (center part of photo) is ready for recycling. View looking west with Griffin Road and the Greenbelt on the left side of the photo.
December 2012 construction of the South Runway
December 2012 - Dynamic compaction signs are visible in the bottom center of the photo. View looking east with the Diagonal Runway at the top.

January 2013
January 2013 - The dynamic compaction crane is working to eliminate the voids in the soil to avoid any settlement later. This view is looking east.
Two dynamic compactors are working. There are two piles of crushed asphalt ready for removal and recycling.
February 2013 - Two dynamic compactors are working. There are two piles of crushed asphalt ready for removal and recycling.

Western view of the South Runway under construction
March 2013 - A tanker truck wets the ground (bottom left of the photo) as part of the dust control plan.
Western view of the South Runway under construction
April 2013 - An excavator at the bottom of the photo is breaking up the limestone ground (fracturing) as part of the ground preparation.