Click images for larger view
Western view of the South Runway under construction taken in March 2014 March 2014 - Pouring of the concrete base layer and top layer continues as the outline of the runway and taxiway take shape.
April 2014 west end of the South Runway April 2014 - Runway paving is complete and workers are placing the cement base on the left side of the photo.
May 2014 western end of the South Runway May 2014 - Placing the top and final layer of cement for the taxiways continues.
Western end of the South Runway under construction in June 2014 June 2014 - The taxiway base layer is complete. Workers place the top layer of concrete.
Western end of the South Runway under construction in July 2014 July 2014 - Concrete paving is almost complete on the taxiway. At the bottom of the photo are the trailer containing the Engineered Material​ Arresting System.
Western end of the South Runway in late August 2014 August 2014 - The Engineered Material Arresting System (EMAS) has been installed on the bottom of the photo. The taxiway at this end is also complete.
September 2014 view of the western parts of the new South Runway ​September 2014 - All the taxiway and EMAS markings are installed.