Current Activities

Construction Activities from August 24 - 29 and August 31- September 5

Contractors will perform the following work:


    


Click on the image for a larger version.
View and/or print a larger Work Area Map (PDF).

Crossfield Taxiways (Areas 3, 4, and 5)

  • Installing drainage, utilities, and lighting.
  • Grading the ground.
  • Placing the base layer and the final top layer of concrete.


Terminal 4 Building and Apron (Area 6)

  • Installing the terrazzo floors and wall tile on the Mezzanine Level.  
  • Completing the interior offices on the third and fourth levels.
  • Placing the apron east of the building.
  • Installing the precast concrete wall panels on the connector bridge between Terminals 3 and 4.

Terminal 3 (Area 9)

  • Completing the terrazzo floor by the ticket counters and security check point for Concourse E.  

Covered Walkways (Area 10)

  • Extending the roof of Terminal 1 to meet the covered walkway. 

 

Look at a larger version of the Construction Area Map (PDF).