Construction Activities from 13 - 18 and October 20 - 25

Contractors will perform the following work:

Runway Structures (Areas 4 and 6)

  • Completing the installation of the mechanical, electrical, piping, and fire alarm systems in the utility building.
  • Installing the ventilation, lighting, fire detection, and fire suppression systems in the tunnels. 

Ramps and Roadwork

  • Building the ramp in Area 1 to I-595 and Port Everglades.
  • Building the airport exit ramp to US 1 southbound in Area 2.  
Map of the work areas
Click on the image for a larger version.

Runway Paving

  • Pouring the base layer in Areas 4 and 5.
  • Pouring the concrete top layer in Areas 4 and 5.
  • Installing utilities, signs, and lights in Areas 5, 6, 10, 11, and 12.

Earthwork

  • Placing top soil and laying sod in Area 10.

Terminal 4 Building and Apron (Area 13)

  • Building the concrete forms on the 3rd level.
  • Pouring concrete on the 3rd level.
  • Installing steel roof deck and joists.
  • Constructing masonry walls.
  • Installing structural steel for concession frames.
  • Placing pre-cast concrete exterior wall panels.
  • Installing electrical and plumbing.
  • Installing the apron drainage.
  • Constructing new retaining and screening walls.

Terminal 3

  • Installing the terrazzo floor on the ticket counter level.
  • Replacing the ceiling and lights in the baggage claim area.
  • Renovating the TSA Check Point at Concourse E.

Look at a larger version of the Construction Area Map (PDF).

Required Plug-ins: PDF iconAdobe® Reader®