Current Activities

Construction Activities from December 22 - 24 and
December 29 - 31

Contractors will perform the following work:


Runway Structures (Area 2)

  • Installing the ventilation, lighting, fire detection, and fire suppression system in the Perimeter Road tunnel. 

Ramp (Area 1) 

  • Building the airport exit ramp to US 1 southbound  

Work areas at FLL

Click on the image for a larger version.

Crossfield Taxiways (Areas 3, 4, and 5)

  • Preparing the ground.  
  • Installing utilities.


Terminal 4 Building and Apron (Area 6)

  • Constructing masonry walls and columns.
  • Installing structural steel for concession frames.
  • Placing pre-cast concrete exterior wall panels.
  • Installing electrical, fire protection, and plumbing.
  • Installing the apron drainage.
  • Installing the terrazzo floor on the main concourse level.

Terminal 3 (Area 9)

  • Installing the terrazzo floor on the ticket counter level.
  • Replacing the ceiling and lights in the baggage claim area.

Covered Walkways (Area 10)

  • Installing covered walkways between Terminals 1, 2, and 3.

 

Look at a larger version of the Construction Area Map (PDF).

Required Plug-ins: PDF iconAdobe® Reader®