Construction Activities from July 17 - 22 and July 24 - 29 

Contractors will perform the following work:
    




Click on the image for a larger version.
View and/or print a larger Work Area Map (PDF).

Terminal 4 (Area 4)

  • Finishing the interior of Concourse G.
  • Installing a bag-recheck counter and handling system.
  • Completing the roof for the Customs area.
  • Installing terrazzo floors in the Baggage Claim area and by the ticket counters.

 Terminal 1 (Area 1)

  • Building the Concession Hall between Concourses B and C and the centralized security checkpoint.

Terminal 3 (Area 3)

  • Installing a baggage conveyor system.

Pedestrian Bridges

  • Installing the handrails and lighting.
  • Refurbishing the terminal vestibule entrances to the bridges. 

 

Look at a larger version of the Construction Area Map (PDF).