Current Activities

Construction Activities from February 1 - 6 and February 8 - 13

Contractors will perform the following work:


    


Click on the image for a larger version.
View and/or print a larger Work Area Map (PDF).

Cross Field Taxiways (Areas 3, 4, and 5)

  • Grading the ground.
  • Placing sod.


Terminal 4 and Apron (Area 6)

  • Finishing the connector bridge between Terminals 3 and 4.
  • Installing utility lines near the connector bridge.
  • Grading and placing concrete under the connector bridge.
  • Installing the equipment, shelving, and seating in the concession areas.
  • Placing the apron's base layer and concrete top layer south and east of the building.

 

 Terminal 1 (Area 7)

  • Utility work.
  • Installing pilings for the foundations.

Terminal 2 (Area 9)

  • Installing a terrazzo floor on the ticket counter level.

Terminal 3 (Area 9)

  • Installing a baggage conveyor system in the baggage claim lower level.

Pedestrian Bridges

  • Removing the old floors.
  • Repairing the steel structure.

 

Look at a larger version of the Construction Area Map (PDF).