Barrier Islands
Story 1
|
|
|
PDF version of the above map
The purpose of the Barrier Islands Greenway is to establish the corridor as one of the most desirable recreation corridors in the County. Continuous multipurpose paths along the beach, the A1A roadway itself and various neighborhood streets will link public beaches, resorts, waterside communities, activity centers, marinas, restaurants, municipal centers and other attractions. Through the use of the appropriate signs and other markers, the Barrier Islands Greenway has the potential to be the premier attraction in South Florida - further enhancing the unique sense of place along the corridor, as well as being an asset to each local neighborhood.
|
| Potential Development Costs |
| The Barrier Islands Greenway |
Cost |
|
1. Roadway Construction Various Locations
|
+$8,400,000 |
|
2. Local Links Various Locations |
+$3,300,000 |
|
3. Beachside Facilities Deerfield Beach |
+$350,000 |
|
4. Future Wide Path Deerfield Beach |
+$150,000 |
|
5. Roadway Reconstruction Hillsboro Beach |
+$5,300,000 |
|
6. Roadway Restriping Various Locations |
+$400,000 |
|
7. Roadway Narrowing Various Locations |
+$3,700,000 |
|
8. Connect to Future Facilities Lauderdale-by-the-Sea |
+$100,000 |
|
9. Connect to Existing Facilities Hillsboro Beach |
+$400,000 |
|
10. Ft. Lauderdale Beach Section |
+$150,000 |
|
11. Alternate Local Links Various Locations |
+$3,700,000 |
|
12. Beachside Path Ft. Lauderdale |
+$500,000 |
|
13. Bridge Crossing Ft. Lauderdale |
+$1,100,000 |
|
14. Other Local Links Various Locations |
+$800,000 |
|
15. Beachside Path Hollywood |
+$400,000 |
|
Grand Total *=Does not include land aquisition costs if applicable or design costs; costs computed using 2001 dollars; estimates for conceptual use only. |
+$28,750,000* | |
Select images below to view PDF version of this document.
|
Required Plug-ins: Adobe® Reader®
|