| January 2013 |
Install deep injection wells Install concrete auger cast piles for the Bridge Start Tower foundations Erect Tower cranes |
| December 2012 |
Install Tower crane pads Dewatering and sheet piles Mobilize Tower cranes Install new drainage along Courthouse Drive |
| December 18, 2012 |
Precast plant quality assurance/quality control site visit |
| December 5, 2012 |
Demo existing drainage along Courthouse Drive |
| Nov.-Dec. 2012 |
Mobilize activities: James A. Cummings (contractor) and Owner’s Construction Project Manager (the Weitz Company) Install concrete auger cast piles for Tower Modify existing 12” water main along Courthouse Drive (added scope) |
| November 26, 2012 |
Install new 16" water main along S.E. 6th Street |
| November 19, 2012 |
Demo existing duct bank, vault, sidewalk and water main along Courthouse Drive |
| November 12, 2012 |
Reconfigure Maintenance of Traffic on 6th Street Install new sanitary sewer along Courthouse Drive |
| October 15, 2012 |
Contractor receives Second Notice to Proceed on elevated walkway between the Courthouse and North Wing building and new elevator core for the west building |
| October 8, 2012 |
Install steel sheet piles along Courthouse Drive |
| September 7, 2012 |
Install concrete test piles |
| September 4, 2012 |
Erect mobile crane for foundation pile work |
| September 1-28, 2012 |
Begin FPL underground electrical work along Courthouse Drive |
| August 22, 2012 |
Begin demolition of West Parking Garage |
| August 21, 2012 |
First Notice to Proceed issued for new Tower |
| August 21, 2012 |
Groundbreaking ceremony held |
| August 20, 2012 |
Plaza area and pedestrian walkway demolished |
| August 18, 2012 |
Install temporary fencing around garage perimeter. Close plaza area. |
| August 2, 2012 |
Close West Parking Garage |
| August 1, 2012 |
First Notice to Proceed issued for garage demo |
| July 2012 |
Initial agreements negotiated and signed |
| June 12, 2012 |
Broward County Commission awards construction contract to James A. Cummings, Inc. |
| May 25, 2012 |
Final set of design plans submitted by The Spillis Candela & Partners/Heery/Cartaya Joint Venture, the project's design consultant |
Please note that dates are subject to change.