2012

​Mobilize activities: James A. Cummings (contractor) and Owner’s Construction Project Manager (the Weitz Company).​​ View Slide Show​
​Install concrete auger cast piles for Tower.
​Modify existing 12” water main along Courthouse Drive (added scope).
​Install new 16" water main along S.E. 6th Street.
Demo existing duct bank, vault, sidewalk and water main along Courthouse Drive.
Reconfigure Maintenance of Traffic on 6th Street.
​​Install new sanitary sewer along Courthouse Drive.​
Contractor receives Second Notice ​to Proceed on elevated walkway between the Courthouse and North Wing building and new elevator core for the west building.
​Install steel sheet piles along Courthouse Drive.
​Install concrete test piles.
​Erect mobile crane for foundation pile work.​
​Begin FPL underground electrical work along Courthouse Drive.
​Begin demolition of West Parking Garage. View Slide Show​
​​First Notice to Proceed issued for new Tower.
​Groundbreaking ceremony held​​.
​Plaza area and pedestrian walkway demolished.
​Install temporary fencing around garage perimeter. Close plaza area.
​Close West Parking Garage.
​First Notice to Proceed issued for garage demo.
​Initial agreements negot​iated and signed​.
​​Broward County Commission awards construction contract to James A. Cummings, Inc.
​​Final set of design plans submitted by The Spillis Candela & Partners/Heery/Cartaya Joint Venture, the project's design consultant.​