2013

13th Floor – 15th Floor concrete slabs complete. View Slide Show​​
​Floors 2-11 framing, rough-ins and equipment are in progress.
Elevator equipment is delivered onsite​.​
Curtain wall system installation is finished for floors 2-4​.
​Architectural precast panels installation through the 5th floor​.
​North Tower Crane jumps to 370 feet.
​Underground utility work on Courthouse Drive.​​​ View Slide Show
​11th Floor – 12th Floor concrete slabs complete.​
​Precast stairs installed through 10th floor.​
​500 KW generator is removed.​
​Audio Visual bid documents are released to James A. Cummings.
​Curtain wall system installation begins at the 4th floor.​
​​Precast stairs are installed through the 5th floor. View Slide Show​
​​Meetings with the user groups regarding fu​​rniture continue.
​Curtain wall system installation begins at the 2nd and 3rd floors.
​Architectural precast panels are installed through the 5th floor.
​10th Floor concrete slabs complete.
​​Air handling units are delivered to the site.
​Review of audio visual bid do​cuments begins.
​​Detention hollow metal door frames underway​.
​6th Floor – 8th Floor concrete slabs complete.
​Meetings with the user groups regarding furniture begin.
​Review of the courtroom mockups begin.
​​2nd floor rough-in of mechanical, plumbing, electrical and fire protection system begins.
​6th floor concrete slab complete.
​​Contractor begins pouring the 6th floor concrete slab.
​​Installation of 22,000 gallon fuel tank for emergency generators.​
​5th floor concrete slab complete.
​​Installation of architectural precast panels begins on ground floor.
​​Final set of design plans submitted by The Spillis Candela & Partners/Heery/Cartaya Joint Venture, the project's design consultant.​