Final connections ongoing for emergency generators ​​and electrical sub-panels. ​View Slide Show
Final connections in process; testing and start-ups beginning for all equipment in the Mechanical Penthouse.
Installation of service elevator near completion which will be used to replace one of the co​nstruction buck hoist.
​Construction by the contractor, James A. Cummings, Inc. is 72 percent complete. View Slide Show
​Final connections of all equipment at the mechanical penthouse (Le​vel 21)
are in process. Testing and Start-ups beginning.
​Final connections of all equipment at the mechanical penthouse (Level 21) are in process.
​​The interior finishes are ongoing at levels 2 through 18.
​Installation of the public’s elevators is ongoing.
​Construction by the contractor, James A. Cummings, Inc. is 69 percent complete.
​The FPL Vault Room is complete and energized.
​Final connections of all equipment at the mechanical penthouse (Level 21) are in process.
​The interior finishes are ongoing at levels 2 through 13.
​​Installation of the prisoners’ elevators is near completion.
​Roofing installation is in process at all levels.​
​The structure of the connector bridge along Courthouse Drive is ongoing.
​While the outside of the new courthouse is al​​most complete, interior work and finishing touches are progressing upwards floor by floor.​ View Slide Show
​Grand Opening of the Judicial Complex South Parking Garage. View Slide Show 1
View Slide Show 2​
​Cooling Tower Support Steel Structure on the roof is complete. View Slide Show
​Mechanical Penthouse, Stair, and Elevator Roof Slabs are complete.
​Architectural Precast Panel Installation up to the parapet is complete.
​Curtain Wall Installation is up to level 19.
​Escalators installation is complete​.
​Elevators are being installed.
​Emergency generators are set. Connections ongoing.
​Florida Power & Light work is ongoing.
​Drywall is ongoing on levels 2 to 6.
​Terrazzo flooring is ongoing on levels 2 to 7.
​Mechanical, electrical, plumbing and fire protection systems are ongoing on levels 7 to 21.
​Cooling Towers delivered to the site and lifted to the mechanical penthouse.
​Elevated bridge along courthouse drive is ongoing and up to the second elevated deck.
​​Curtain wall system installation is finished up to Level 15. ​View Slid Show​
​Drywall, finishe and trim are in progres​s up to Level 7.
​Architectural precast panels have been installed through the 18th Floor.
​Equipment for Elevators 13 and 14 are installed through Level 14.
​Phase 1 Finishes are up to Level 17; Phase 2 Finishes are up to Level 5.
​Framing, rough-ins and equipment are in progress through Level 19.
​Fabrication of duct work is in production through the 18th Floor.
​Cooling tower concrete beams are complete.
​Installation of the Terrazzo flooring has begun.
​​Elevated deck for the Bridge at Courthouse Drive has begun.
​Commercial door and frame fabrication is 95 percent complete.
​Employee Town Hall Meeting Pres​entation (PDF)​. View Slide Show
​Tour of new courthouse construction site Courthouse Progress and Tour Presentation (PDF).
​Topping Off milestone.
​Es​calators are on site.​​
​Fabrication of commercial door frames and doo​​rs in full production.
​Fabrication of duct work is in​​ production through the 12th Floor.​
​Precast stairs installed through the 17th Floor.​
​20th Floor concrete slab complete.​
​Architectural precast panels have been installed through the 11th Floor.​
​​​Level 2 drywall, finishes, and trim are in progress for Level 2.
​Framing, rough-ins, and equipment are in progress through Level 15​.​
​​Curtain wall system installation is finished for Level 6.
​​Structural steel on the Entrance Canopy is complete.​
​Elevator equipm​​ent and air handling units through Level 14 are onsite.​
​Relocation planning for user groups begins.​
​17th floor – 19th Floor concrete slabs complete.​
​​​Curtain wall system installation is finished for Level 5.
​Framing, rough-ins, and equipment are in progress through Level 14.​
​Architectural precast panels have been installed through the 9th Floor.