2015

Ongoing finishing touches made to the building’s interior. ​View Slide Show​
​AT&T begins to install connec​tions throughout the building.
​Signage for life safety equipment is being installed.
​Systems office furniture and furniture for private offices is being
installed on floors 15-18.
​​Pre-cast panels are being installed on the new East Wing elevator core.
​Elevators and escalators are completed.
​Pre-testing of life safety systems and commissioning of equipment is ongoing.
​Systems office furniture is being installed on floors 12-14.
​Work continues on the new East Wing elevator core.
​Fire alarm testing is ongoing.
​Systems office furniture is being​​ installed on floors 9-11.
Terrazzo flooring is being installed in the main lobby.
​Furniture not being supplied by the contractor goes out to bid.
​Atrium wall and mosaic in the main lobby are near completion.
​Systems office furniture is being delivered and installed on floors 2-8.
​Insulation and waterproof membrane is being installed on the new pedestrian bridge.
​Work is in progress on the new East Wing elevator core.​
​Finishes ongoing at elevator lobbies at levels 1-20. View Slide Show
​Work on the East Wing Lobby and Storefront begins.
​Installation of the atrium ceiling at level 6 is ongoing.
​Work in progress at the temporary secured walkway across Courthouse Drive.
​Installation of the lobby atrium ceiling at level 6 is ongoing. View Slide Show
​Mosaic tile for the lobby is approved.
​Removal of the south buck hoist begins.
Curtain wall installation begins at the east buck hoist opening.
​Fabrication of commercial door frames and doors are complete. View Slide Show
​Architectural woodwork installation ongoing on levels 2-10.
​Mechanical Penthouse equipment is operational at select units.
Installation of terrazzo flooring continues on level 2-20.