2015 - Winter

February 2015

Finishes ongoing at elevator lobbies at levels 1-20.​​ View Slide Show
Work on the East Wing Lobby and Storefront begins.
Installation of the atrium ceiling at level 6 is ongoing.
Work in progress at the temporary secured walkway across Courthouse Drive.

January 2015

Installation of the lobby atrium ceiling at level 6 is ongoing. ​​View Slide Show
Mosaic tile for the lobby is approved.​
Removal of the south buck hoist begins.
Curtain wall installation begins at the east buck hoist opening.

December 2014

Fabrication of commercial door frames and doors are complete. View Slide Show
Architectural woodwork installation ongoing on levels 2-10.
Mechanical Penthouse equipment is operational at select units.
​Installation of terrazzo flooring continues on level 2-20.
​​​​