2013 - Fall

October/September 

October

13th Floor – 15th Floor concrete slabs complete
Floors 2-11 framing, rough-ins, and equipment are in progress
Elevator equipment is delivered onsite

​View Slide Show
​Oct. 17

​Curtain wall system installation is finished for floors 2-4
Architectural precast panels installation through the 5th floor

Oct. 13 North Tower Crane jumps to 370 feet
September

Underground utility work on Courthouse Drive
11th Floor – 12th Floor concrete slabs complete
Precast stairs installed through 10th floor

​Sept. 25 ​500 KW generator is removed
​Sept. 18 ​Audio Visual bid documents are released to James A. Cummings
Sept. 15 Curtain wall system installation begins at the 4th floor