May/April/March

May

Installation of sheet piles for the 22,000 gallon fuel tank for emergency generators

View Slide Show​
May 31 Installation of precast stairs complete to 4 th floor
May 14

4th floor concrete slab complete

May 7 Contractor begins pouring 5th floor concrete slab
May 1 Contractor begins pouring the 4th floor concrete slab
​April ​Courthouse tower foundations are completed
​April 24 ​3 rd floor concrete slab completed
​April 17 ​Curtain wall assemblies tested for large missile impact testing at lab
​April 15 ​Contractor begins pouring the 3rd floor concrete slab
​April 10 ​2 nd floor concrete slab complete
​April 2 ​Curtain wall assemblies tested for small missile impact testing at lab
​March ​Planning begins for the courthouse audio visual systems
​March 23 ​1st post-tension stressing of concrete slab
​March 19 ​Contractor begins pouring 2nd floor concrete slab