April/May

Cooling Tower Support Steel Structure on the roof is complete ​View Slide Show
Mechanical Penthouse, Stair, and Elevator Roof Slabs is complete
Architectural Precast Panel Installation up to the parapet is complete
Curtain Wall Installation is up to level 19
Escalators installation is complete
Elevators are being installed
Emergency generators are set. Connections ongoing
Florida Power & Light work is ongoing
Drywall is ongoing on levels 2 to 6
Terrazzo flooring is ongoing on levels 2 to 7
Mechanical, electrical, plumbing and fire protection systems are ongoing on levels 7 to 21
Cooling Towers delivered to the site and lifted to the mechanical penthouse
Elevated bridge along courthouse drive is ongoing and up to the second elevated deck

March

March 31 Curtain wall system installation is finished up to Level 15 View Slide Show
March 27 Drywall, finishe and trim are in progress up to Level 7