2013 - Summer

August/July/June

​August

​Precast stairs are installed through the 5th floor
Meetings with the user groups regarding furniture continue

View Slide Show​
Aug. 25 Curtain wall system installation begins at the 2nd and 3rd floors
Aug. 21 Architectural precast panels are installed through the 5th floor
Aug. 19 10th Floor concrete slabs complete
​July

​Air handling units are delivered to the site
Review of audio visual bid documents begins

​July 30 ​Detention hollow metal door frames underway
July 25 6th Floor – 8th Floor concrete slabs complete
July 15

Meetings with the user groups regarding furniture begin
Review of the courtroom mockups begin

​June ​2nd floor rough-in of mechanical, plumbing, electrical and fire protection system begins
​June 25 ​6th floor concrete slab complete
​June 12 ​Contractor begins pouring the 6th floor concrete slab
​June 11 ​Installation of 22,000 gallon fuel tank for emergency generators
​June 4 ​5th floor concrete slab complete
​June 3 ​Installation of architectural precast panels begins on ground floor