2014 - Winter

February/January/December

February 28 Employee Town Hall Meeting
Presentation (PDF)
View Slide Show​
February 21 Tour of new courthouse construction site
Courthouse Progress and Tour Presentation (PDF)
February Topping Off milestone
January Escalators are on site
Fabrication of commercial door frames and doors in full production
Fabrication of duct work is in production through the 12th Floor
Precast stairs installed through the 17th Floor
​Jan. 20 ​20th Floor concrete slab complete
​Jan. 17 ​Architectural precast panels have been installed through the 11th Floor
​Jan. 14 ​Level 2 drywall, finishes, and trim are in progress for Level 2
​Jan. 7 Framing, rough-ins, and equipment are in progress through Level 15​
​Jan. 2 ​Curtain wall system installation is finished for Level 6
​December 2013 ​Structural steel on the Entrance Canopy is complete
Elevator equipment and air handling units through Level 14 are onsite
Relocation planning for user groups begins
17th floor – 19th Floor concrete slabs complete
​Dec. 23 ​Curtain wall system installation is finished for Level 5
Dec. 19​ Framing, rough-ins, and equipment are in progress through Level 14​
​Dec. 12 ​Architectural precast panels have been installed through the 9th Floor