Central County Neighborhood Improvement Project

The Central County Neighborhood Improvement Project (CCNIP) includes
1,682 acres, 21,300 residents, and 5,029 homes with
3,678 septic tanks. The planned improvements for
the area include 53 miles of roadways, 35 miles
of sidewalk, and 84 miles of pipeline and is split
into 12 construction packages. Neighborhoods include:
Melrose Park, Broward Estates, St. George, Washington
Park, Boulevard Gardens, and Franklin Park. Construction
started in 1999 and is expected to be complete in
2010.
Construction has begun in the CCNIP and will include
improvements in water, sewer and drainage systems, installation of sidewalks,
and neighborhood entrance signs. Additional fire hydrants will be added
throughout six impacted neighborhoods. These areas include St. George, Broward
Estates, Melrose Park, Boulevard Gardens, Washington Park, and Franklin Park.
These areas are bounded by Sunrise Boulevard to the north, Jackson Boulevard to
the south, State Road 7 to the west, and NW 24th Avenue to the east.
With the exception of those properties still on septic tanks that
require the owner to incur the cost to hook up to the sanitary sewer system
after the system is installed, the cost of the remaining work in this project
will be borne entirely by Broward County.
| 35 Avenue
Ditch |
|
| Bid Package 3 |
This project is complete. |
|
|
| Melrose
Park |
|
| Bid Package 1 (NW
Phase 2)
|
This project is complete.
|
|
|
| Bid Package 4 (SW
Quadrant)
|
This project is complete. |
|
|
| Bid Package 10 (SE
Quadrant) |
Construction began May 10, 2007 and is scheduled to be completed by the 4th Quarter of 2008. |
|
|
| Bid Package 12 (NE
Quadrant) |
This project is scheduled to begin the 3rd quarter of 2008 and be completed by the 3rd quarter of 2010. |
|
|
| Franklin Park |
|
| Bid Package 2 |
This project is complete. |
| |
|
| Washington
Park |
|
| Bid Package 5 |
This project is complete. |
| |
|
| Broward Estates |
|
| Bid Package 6
West) |
This project is complete. |
| |
|
| Bid Package 7
(East) |
This project is complete.
|
| |
|
| St. George |
|
| Bid Package 8 West)
|
This project is complete. |
| |
|
| Bid Package 11(
East) |
This project is complete. |
| |
|
| Boulevard
Gardens |
|
| Bid Package 9 |
This project is complete. |
If you have any questions or concerns regarding this
project, please contact Patricia Henry Mullins at (954) 831-3281.
Other Neighborhood Improvement Projects
- NAGNIP - NCNIP -
SCNIP - RVNIP -
NCCNIP - BENIP -
BPNIP
To
Neighborhood Improvement Program Home Page
To
Project & Community Coordination Division Home Page
Back