​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

​​​​​​​​​​​Segment III - Broward County Shore Protection Project

The U.S. Army Corps of Engineers (USACE) completed a Segment III Beach Renourishment project in April 2024. The project area was along the shorelines of Dr. Von D. Mizell-Eula Johnson State Park, Dania, Hollywood, and Hallandale Beaches. The project had a 100% cost share by the federal government through their Flood Control and Costal Emergencies (FCCE) program in response to recovery from Hurricane Irma. Vegetated dunes were constructed in the State Park by USACE. The next phase of the project will be dune construction, funded by Broward County, along the beaches in Dania Beach, Hollywood, and Hallandale Beach.

Progress

The County has awarded the Segment III Dune Project to Dickerson Florida.

The project will add an additional 50,000 cubic yards of sand to upland project areas and will plant approximately 300,000 native dune plants to stabilize the beach.​​​​​

​​

Segment3.jpg
If you have any questions about the County's beach program, please contact Stephanie Roche at sroche@broward.org.

​Contractor Schedule

Contractor staging in the parking lot between Bougainvilla Ter. and Azalea Ter. (Hollywood): Expected January 20-April 30

  • Reduced parking at this location during the dates indicated above.
  • Please abide by all contractor signage and direction during construction to ensure your safety. We appreciate your cooperation.​

Mobilization at Meade St. (Hollywood): Expected January 20-February 20

  • Sand placement from Dania Pier to Meade St. à approx. January 20-30 (working north to south)
  • Sand placement from Meade St. to Cleveland St. à approx. February 2-20 (working south to north)

*For public safety, beach access may be temporarily closed at Meade St. during sand delivery. Nearby accesses will not be impacted by construction. Please abide by all contractor signage and direction during construction to ensure your safety. We appreciate your cooperation.​

No dunes will be constructed from Cleveland St. to Harrison St. in Hollywood as part of this project
Mobilization at Bougainvilla Ter. (Hollywood): Expected February 23-March 27

  • Sand placement from Harrison St. to Bougainvilla Ter. à approx. February 23-27 (working north to south)
  • Sand placement from Bougainvilla Ter. to southern Hollywood à approx. March 2-27 (working south to north)

*For public safety, beach access may be temporarily closed at Bougainvilla Ter. during sand delivery. Nearby accesses will not be impacted by construction. Please abide by all contractor signage and direction during construction to ensure your safety. We appreciate your cooperation.

Mobilization at South City Beach Park (Hallandale): Expected March 30-April 24

  • Sand placement from South City Beach Park à approx. March 30-April 10 (order of construction TBD)

*For public safety, the southern beach access at South City Beach Park may be temporarily closed during sand delivery. We expect the northern pedestrian access at South City Beach Park to remain open for use. Please abide by all contractor signage and direction during construction to ensure your safety. We appreciate your cooperation

The above schedule is subject to change and will be updated as the project progresses.