Project Information

​​​​​​​​​​​​

Awarded Municipal Capital Projects - Fiscal Years and creation of Five-Year Plan


On May 22 and June 4, 2020, surtax-funded staff at the MPO presented a ranked list of recommended capital projects to the Oversight Board for eligibility review. The original list contained 110 municipal capital projects (MCPs), including 33 projects considered construction-ready and 77 projects in either planning or design phases. Ultimately, 97 MCPs were deemed eligible and recommended by the Oversight Board to the County Commission, 63 of those projects were in a Planning or Design phase; the next phases of those projects became the foundation of the first Five-Year Plan (FYs2021-2025) which was presented to the Oversight Board on August 14, 2020; $126.9 million was included in the county’s FY2021 Capital Budget approved in September 2020. The rolling Five-Year Plan continues funding MCPs based on the rank order of that original list of MCPs. Six capital projects retain their ranking but have yet to be presented to the Oversight Board for an eligibility determination at the sponsoring municipalities’ requests. One originally deferred project was reviewed in 2021, presented and approved by the Oversight Board, and recommended for funding in FY 2022 due to its high ranking. 

For more information about Municipal Capital Project details, scroll to the bottom of this page.



Five-Year Plan Municipal Capital Projects (Fiscal Years 2023 - 2027​)

​​

The Municipal Five-Year Plan includes recommended funding for subsequent phases of capital projects approved by the County Commission in Cycle 1 (2020) for planning and design phases. In addition, the plan reflects the removal of projects by sponsors (municipalities) as well as projects moved ahead of schedule due to efficiency and cost-savings considerations. 

The Five-Year Plan acts as the basis for annual surtax funding appropriations and offers recipients of surtax funds a level of certainty in long-range programming and planning for transportation projects and surtax revenues. The 2022-2026 update includes funding for 28 projects, 26 of which will be fully funded. The primary criteria for inclusion in the Five-Year Plan was the project’s ranking and the expected availability of funds.

The Second Amendment to the Interlocal Agreement guarantees a Minimum Annual Guarantee (MAG) funding commitment to utilize at least ten percent (10%) of the Transportation Surtax Proceeds received by the County each Fiscal Year to fund Community Shuttle Service, Municipal Capital Projects, Municipal R&M Projects, and Municipal Project Contingency.

The image below shows the amount of surtax funds budgeted for municipal projects exceeding the MAG funding within the five-year plan.  


5ypbudget.JPG


Surtax Municipal Capital Projects Five-Year Plan FY2022-FY2026

The chart below shows surtax expenditures in the Five-Year Plan totaling $154.4 Million in 7 categories:​

  • Roadway Resilience: $4.8 M
  • Transit Infrastructure (bus stops and shelters): $​6.9 M
  • Multi-Use Paths/Greenways: $7.2 M​
  • Safety Improvements: $8.3 M
  • Roadway Improvements: $37.3 M
  • Bicycle and Pedestrian Facilities: $42.6 M
  • Congestion Management, roadway expansion/widening: $47.3 M​

mcp5yp2226.JPG


Awarded Municipal Rehabilitation and Maintenance Projects - Fiscal Year 2020 (Cycle 1)


The Oversight Board also reviewed and deemed 62 R&M projects eligible, on June 4, 2020. County Commission approved 40 R&M (construction only) projects to be included in Cycle 1, for a total not-to-exceed amount of $55.5M.


For more information about Municipal Rehabilitation & Maintenance project details, scroll to the bottom of this page.


Municipal Capital Project Details
Awarded Funding
Not-to-exceed amount

​​Project Ranking 
​Municipality
​Project ID
​Project Name
Funded Phase
​Current Surtax Award for Phase
​Project Funding Agreement Status​
​Solicitation 
Status
​1
​Wilton Manors
​WILT-006
NE 26th St Improvements ADA Access
​Construction 
​$310,564.72*​
​Executed - Project Underway​
​Bid Awarded
​2
​Sunrise
​SUNR-025.1
​Various drainage improvements
​Construction
​$5,180,000
In Progress
​Not Started
​3
​Pompano Beach
​POMP-004
​Bay Drive neighborhood stormwater improvements 
​Construction
​$1,174,741
​Executed - Project Underway
​Not Started
​4
​North Lauderdale
​NLAU-007.1
​Neighborhood traffic calming program
​Construction
​$1,998,187
​Executed - Project Underway
​Bid Awarded
​5
​Weston
​WEST-224
​Intersection Improvements Royal Palm Blvd & Weston Rd
​Construction
​$1,612,082
​Executed - Project Underway
Bid Awarded
​6
​West Park
​WPRK-004
​SW 25 St Complete Street improvements
Construction
​$1,638,987
Executed - Project Underway
Bid Awarded
​7
​Coral Springs
​CORA-115.1
​Emergency traffic signals
​Construction
​$556,050
Executed - Project Underway
​Not Started
​8
​Dania Beach
​DANI-019
​Stormwater improvements 
​Construction 
​$2,076,875*
​Executed - Project Underway
​Closed Bid
​9
​Davie
​DAVI-003
​Davie Rd improvements phase III
​Construction
​$4,108,705*
​Executed - Project Underway

Bid Awarded
​12
​Cooper City
​COOP-036
​Way finding signs
​Construction
​$30,000
​Not Started
​Not Started

13
​Hallandale Beach
​HALL-026
​City-wide bus stops digital signage
​Construction
​$513,600
​Not Started
​Not Started
14
​Deerfield Beach
​DEER-003
​Citywide pedestrian street lighting improvements
​Construction
$800,000​
In Progress
​Not Started
15
​Southwest Ranches
​SWRA-032
​Drainage Project: SW 50 St & SW 182 Ave
​Construction

$124,000
Project ​Completed
Project Completed
​16
​Oakland Park
​OAKL-099
​Landscape improvements on medians of Oakland Park Blvd from NW 31 Ave to NW 21 Ave (Phase II)​
​Construction
$330,006*
​Project ​Completed
​Project ​Completed
17
​Hollywood
​HOLL-064
​Industrial Park and corridor improvements
​Construction
​$5,000,000
Not Started
​Not Started
​18
​Pembroke Park
​PPRK-002
​SW 25th St Stormwater Improvements (Phase II)
​Construction
​$1,272,115
​Not Started
​Not Started
​19
​West Park
​WPRK-007
​SW 57 Ave & SW 20 St Traffic calming improvement
​Construction
​$163,519
Not Started
​N/A

20 

Fort Lauderdale
FORT-122
​NW 15th Ave Safety and mobility improvements & Street Lighting (FORT-122 & FORT-162 Bundled)​
​Construction 
​$2,996,668
In Progress
​Not Started
​21

​Tamarac
​TAMA-003.1
​70th Avenue Traffic Calming Project
​Construction
​$528,902
​Executed - Project Underway
​Bid Awaded

22
​Wilton Manors
​WILT-012
​NE 15th Ave & NE 24th Complete Streets
​Construction
​$516,975.49*
Executed Project Underway
​Bid Awarded

​23

​Pompano Beach
​POMP-006
​Kendall lake neighborhood stormwater improvements
​Construction
​$3,741,868
​In Progress
​Not Started
24
​Hallandale Beach
​HALL-005
​​City-wide bus shelter improvements
​Construction
​$2,977,563
​Not Started
​Not Started
25
​Davie
​DAVI-001
​College Ave Phase II widening
​Construction
​$1,000,000
​Executed - Project Underway
​Bid Awarded
26
​Hollywood
​HOLL-035
​Hollywood Blvd from East end of City Hall Circle to Dixie Hwy Complete Streets Improvements
​Construction
​$700,000
Executed - Project Underway
​Bid Awarded
27
​Lauderdale Lakes
​LLAK-015
​NW 36 Terrace improvements
​Construction
​$863,663
​Not Started

​Not Started
28
Weston
​WEST-308
​Indian Trace elementary school
​Construction
​$319,086
​Executed - Project Underway
Bid Awarded
30
Weston
​WEST-307.1
​City-wide wayfinding signage program
Construction​​$181,039*
​Executed - Project Underway
Bid Awarded
31
​Tamarac
​TAMA-014
​Traffic control devices
​Construction
​$445,817
​​Executed - Project Underway
​Not Started

33
​Wilton Manors
​WILT-013
​Electronic message boards / wayfinding
​Construction
​$639,650
​In Progress
​Not Started
34
​Miramar
​MIRA-001
​Miramar Pkwy and Pembroke Rd expansion (MIRA-001; MIRA-002; MIRA-003; and MIRA-004)
​Design
​$7,730,000*
Executed - Project Underway
Bids Awarded
38
​Fort Lauderdale
​FORT-108
​Safety improvements in Andrews Ave (FORT-108 bundled with FORT-113)
​Planning
​$195,000
​In Progress
​Not Started
39
​Oakland Park
​OAKL-023
​City-Wide Mast Arm Conversion
​Design
​$942,610.70*
​Executed - Project Underway
​Bids Under Evaluation
40
​Coral Springs
​CORA-097
​New sidewalk construction
​Planning
​$600,000
Deemed Ineligible - Not Formally Withdrawn
41
​Coconut Creek
​COCO-024
​New bus shelters and shelter improvements to meet ADA standards
​Design
​$432,000
Executed - Project Underway
​Bids Under Evaluation
42
​Pompano Beach
​POMP-002
​Dixie Hwy/Atlantic Blvd improvements
​Construction
​$24,860,000
In Progress
​Not Started
43
​Hollywood
​HOLL-036
​Complete streets - State Rd 7
​Design
​$120,000
Not Started
​Not Started
44
​Davie
​DAVI-016
​Orange Dr Corridor Enhancements
​Design
​$360,000
​Executed - Project Underway
​Bids Under Evaluation
45
​Miramar
​MIRA-021
​Pembroke Rd Bike Lane
​Planning
Withdrawn by Municipality
Withdrawn by Municipality
​N/A
46
​Pembroke Pines 
​PPIN-039 
​City-wide sidewalk project
​Planning
​$132,938
​Not Started
​Not Started
47
​West Park
​WPRK-002
​Pedestrian Lights - State Rd 7
​Design
​$90,000
​Executed - Project Underway
​Bid Awarded
48
​Lauderdale Lakes
​LLAK-006
​Comprehensive Traffic calming program
​Planning 
​$25,500
​In Progress
​Not Started
​49
​Wilton Manors
​WILT-009
​Bus benches and shelters
​Planning
​$180,000
​Deemed Ineligible - Not Formally Withdrawn
​N/A
​50
​Sunrise
​SUNR-055
​Pine Island Rd bicycle Lanes
​Design
​$540,000
​Not Started
​Not Started
51

​Pembroke Park
​PPRK-010
​Bike Lane and sidewalk improvements
​Design
​$30,000
Not Started
​Not Started
52
Lauderdale-By-The-Sea
​LSEA-005
​El Mar Drive improvements
​Construction
​$2,000,000
Not Started
​Not Started
53
​Weston
​WEST-303
​Weston Rd corridor RRR
​Design
​$588,000
Executed - Project Underway
​Continuous Service
54
​Deerfield Beach
​DEER-007
​FAU Research Blvd Roadway Improvements
​Design
​$480,000
Executed - Project Underway
​Bid Awarded​
56
​Tamarac
​TAMA-008
​Bike Lanes
​Planning
​$135,000
In Progress
​Not Started
57

​Lighthouse Point
​LHP-010
​Construction new sidewalks and bike lane on NW 36th St (Sample Rd); Sample Rd from US1 to NE 23rd Ave; corridor safety and traffic calming ; Sidewalk Construction
(Bundled LHP-010, LHP-009, LHP-011) ​
​Planning
​$67,500
​In Progress
​Not Started
58
​North Lauderdale
​NLAU-007.2
​Neighborhood Traffic Calming Program
​Design
​$302,110*
​Executed - Project Underway
​Bid Awarded
59

​Parkland
​PARK-008
​Construction of Bike Lanes on Parkside Drive
​Design
Withdrawn by Municipality
Withdrawn by Municipality

​N/A
60
​Dania Beach
​DANI-001
​Design and construction of new Bridge on West Dania Beach Blvd Over the C-10 Canal
​Design
Withdrawn by Municipality
Withdrawn by Municipality
​N/A
61
​Margate
​MARG-002
​Winfield Blvd improvements
​Design
​$20,880
In Progress
​Not Started
63
​Fort Lauderdale
​FORT-104
​Sidewalk Program: Construction of New Sidewalks
​Design
​$360,000
Deemed Ineligible - Not Formally Withdrawn
​N/A
64
​Oakland Park
​OAKL-007
​CSX and FEC Crossing Study
​Planning
​$150,000
​In Progress
​Not Started
65
​Coral Springs
​CORA-098
​New Sidewalk Construction
​Planning
​$600,000
Deemed Ineligible - Not Formally Wihtdrawn
​N/A
66
​Hollywood
​HOLL-038
Complete Streets - Johnson St
​Planning
​$150,000
​Not Started
​​Not Started
67
​Miramar
​MIRA-020
​Bus Shelter Improvement
​Design
​$144,000
​In Progress
​​Not Started
68
​Lauderdale Lakes
​LLAK-016
​NW 50th Ave Improvements Study & Design
​Planning
​$15,000
​In Progress
​​Not Started
69
Sunrise
​SUNR-075
​Oakland Park Blvd Multi-Use Path (Bundled with SUNR-061)
​Design
​$1,110,000
​In Progress

​​Not Started
​71
​Davie
​DAVI-012
​SW 30th St improvements
​Design 
​$240,000
Executed - Project Underway
​​Not Started
73
​Wilton Manors
WILT-003
​Complete Streets - Safety Improvements
​Design
​$240,000
Executed - Project Underway
​Bid Awarded​
​74

​West Park
​WPRK-003
​SW 48 Ave Complete Streets
​Design
​$420,000
​Executed - Project Underway
​Bid Awarded
75
West Park​WEST-192
​Indian Trace Road Improvements
(WEST-192 bundled with WEST-193)
​Design
$369,000​*
Executed - Project Underway
​Continuous Service
​76
Pembroke Park​
​WPRK-009
​52 Ave Complete Streets
​Design
​$144,000
​Not Started
​Not Started
​77
Deerfield Beach​
DEER-005​​Pioneer Grove improvements - Pedestrian Lighting (DEER-005 & DEER-006 Bundled)​
​Design
​$300,000
Executed - Project Underway
​Bid Awarded

80

North Lauderdale​​NLAU-008
​SW 64th Ter Sidewalk and Traffic Calming
​Design
​$218,290*
Executed - Project Underway
​Bid Awarded​
81
Cooper City​​COOP-024
​Storm Water Drainage Improvement
​Design
​$480,000
Executed - Project Underway
​​Not Started
82​
​Parkland
​PARK-002
​Lox Road Improvements
Construction
​$2,338,020*
​Executed - Project Underway
Not Started
​83
​Margate
​MARG-047
​City Bicycle / Pedestrian Greenway System
​Design
​$120,000
​Not Started
​Not Started
84​

​Southwest Ranches
​SWRA-022
​Drainage Project: Green Meadows
​Construction
​$43,000
Executed - Project Underway
​Bids Under Evaluation
85​

​Tamarac
​TAMA-001
​Multimodal Connectivity Plan
​Planning
​$120,000
Executed - Project Underway
​Not Started
87​

Dania Beach
​DANI-017
​SE Stormwater Drainage System
​Design
​$865,440
​Executed - Project Underway
​Bid Awarded
89​

​Coral Springs
​CORA-102
​Bus Shelter Repair and Replacement
​Design
​$45,000
Not Started
​Not Started
90​

​Miramar
​MIRA-025
​Pembroke Road Bike Lane
​Design
​$252,000
Executed - Project Underway
​Open Bid

93​
​Lauderdale Lakes
LLAK-018​
​NW 36 St Improvements
​Design
​$120,000
In Progress

​Not Started
​94

​Hallandale Beach
​HALL-019
​NW/SW 8th Ave Complete Street
​Design
​$180,000
In Progress
​Not Started
95​

​Davie
​DAVI-014
​Nova Dr Improvements
​Design
​$336,000
In Progress
​Not Started
96​

​Coconut Creek
​COCO-016
​Sample Rd Multi-Purpose path
​Design
​$330,600
Not Started
​Not Started
97​

​West Park
​WPRK-008
​SW 21st Street Complete Street Improvement
​Design
​$240,000
​Executed - Project Underway
​Bid Awarded
99​

​Pompano Beach
​POMP-013
​Riverside Drive Improvements
​Design
​$711,450*
Executed - Project Underway

​Bid Awarded
102
Pembroke Park
​PPRK-008
​County Line Road -​ Storm Water Connection​
​Design
​$90,000
​Not Started
​Not Started

106​
​Parkland
PARK-007​
​Traffic light - Hillsboro Blvd and University Dr
​Construction
​$600,000
​Not Started
​Not Started
​107
​Margate
​MARG-033
​Firefighters Pk-Winfield Blvd. Bridge
​Design
​$24,000
​Deemed Ineligible - Not Formally Withdrawn
​N/A
108

​Southwest Ranches
​SWRA-037
​Drainage Project: Dykes Road and SW 51st Manor
​Design
Withdrawn by Municipality
Withdrawn by Municipality
​N/A
​109

​Hollywood
​HOLL-056
​Transportation/Traffic Calming - District 5
​Design
​$100,000
In Progress
​Not Started
C 3-1
​Miramar
​MIRA-017


​Design
​$506,520
​Not Started
​Not Started
​C 3-2

​West Park
​WPRK-001


​Design
​$115,400
​Not Started
​Not Started
​C 3-3 

​Davie
​DAVI-019


​Design
​$370,416
​Not Started
​Not Started
​C 3-4

​Weston
​WEST-312


​Design
​$1,181,617
​Not Started
​Not Started
​C 3-5

​Davie
​DAVI-002


​Design
​$367,726
​Not Started
​Not Started
​C 3-6

​Oakland Park
​OAKL-22-004


​Design
​$471,137
​Not Started
​Not Started
​C 3-7

​Davie
​DAVI-011


​Design
​$331,979
​Not Started
​Not Started
​C 3-8

​Lauderhill
​LHIL-518


​Design
​$511,562.87
​Not Started
​Not Started

Notes:

  • Projects were ranked in accordance to Section IV.A. of of the Second Amendment to the Transportation System Surtax Interlocal Agreement
  • ​Information provided as of November 2022
  • Projects #C3-1 to C3-8 are Cycle 3 MPO MCP Funding Recommendations pursuant to Section IV.B.1 of the Second Amendment to the Transportation System Surtax Interlocal Agreement
  • PFA Status​
    • ​Not Started: Municipality has not submitted a completed document packaged as established by Surtax Legal Counsel guidelines​
    • ​In Progress: Surtax Legal Counsel Team has received all required information and project documentation is under review. May require additional municipal submissions and actions.
    • Executed – Project Underway: Agreements have been finalized and projects’ current phases are in progress. 
  • Solicitation Status:
    • Bid Awarded: Municipality selected winning bid 
    • ​Bids Under Evaluation: Bidding window closed, and municipality is reviewing bids
    • Open Bid: Municipality has an open bid 
    • Closed Bid: Municipality has closed bidding
    • Pending Solicitation- Municipality will be posting solicitation soon 
    • Continuous Services- Municipality received approval from County to utilize an existing agreement compliant with surtax terms and conditions​

*Amounts reflect revised funding included in executed Project Funding Agreements.

For more detailed information on municipal capital projects, click HE​RE.​




Awarded Municipal Rehabilitation and Maintenance Project Details
Awarded Funding
Not-to-exceed amount
​​Project Ranking
​Municipality
​Project ID
​Project Name​
​Awarded Funding
(Not-to-exceed)
Project Funding Agreement Status
​​Solicitation Status
​1
Lauderhill​LAHILL-R&M-01
​City of Lauderhill Sidewalk Repair Project
​$15,500
Deemed Ineligible - Not Formally Withdrawn
​N/A
​2
Plantation​PLANT-R&M-02
​Plantation Roadway Resurfacing Projects
​$2,749,823
​Executed - Project Underway
​Bid Awarded
​3

Fort Lauderdale​
FTLAUD-R&M-02
​South Ocean Drive Bridge Repair Project
​$2,176,937*
​Executed - Project Underway
Bids Under Evaluation
​4
Hollywood​
​HLYWD-R&M-02
​Resurfacing of North 58th Ave and Sidewalk Repairs Project
​$1,013,807*
​Executed - Project Underway
​Bid Awarded
​5
​Fort Lauderdale
FTLAUD-R&M-04
​West Lake Drive Bridge Repair Project
​$1,617,300
​Not Started
​​Not Started
​6
​Hollywood
​HLYWD-R&M-01
​Sidewalk, Pavement and Arterial Resurfacing Project
​$2,967,457
​Executed - Project Underway
​Bid Awarded
​7
Tamarac​
TAM-R&M-01
​​Milling, Paving and Resurfacing of Mainlands Section 1-5 Subdivision 
​$2,817,339
Executed - Project Underway
Not Started

​8
​Coconut Creek
CCREEK-R&M-01
​Milling, Paving, and Resurfacing of Public Roads
​$3,000,000
​Executed - Project Underway
​Bid Awarded
​9

​Deerfield Beach
​DFBEACH-R&M-01
​SE 13th Avenue Bridge Repair Project
​$749,890*
Executed - Project Underway
​Bid Awarded​
10
​Southwest Ranches
​SWRANCHES-R&M-03
​Resurfacing and roadway improvements II
​$1,223,165
Project Completed
Project Completed
​11

​Lighthouse Point
LHPOINT-R&M-01
​NE 24th Ave Bridge Replacement Project
​$913,588
​Not Started
Not Started
12
​Oakland Park
OAKLAND-R&M-01
​Oakland Park Roads and Local Collectors Resurfacing Project 
​$2,981,440
​In Progress
Not Started
13

​Miramar
MIRAM-R&M-03
​City of Miramar Roadway resurfacing project III
​$2,234,426
In Progress​​Not Started
​14


​Southwest Ranches
SWRANCHES-R&M-02
​Resurfacing and roadway improvements I
​$737,005​
Project Completed
Project Completed
15
Hollywood​
​HLYWD-R&M-03
​Liberty Street Sidewalk Repairs and ADA Upgrades Project
​$1,010,000*
Executed - Project Underway
​Bid Awarded
​16
Hallandale Beach​​HBEACH-R&M-01
​Hallandale Beach Sidewalk Repair Project
​$2,971,710
Deemed Ineligible - Not Formally Withdrawn
​N/A
​17
Oakland Park​
OAKLAND-R&M-02​
​Andrew Gardens Drainage Improvements Project
$2,072,800
​Not Started
Not Started
​18
Miramar
​MIRAM-R&M-02
​City of Miramar Roadway resurfacing project II
​$1,854,177
​In Progress
Not Started
​19
​Weston
WESTON-R&M-04
​Sidewalk Repairs and Replacement Project 
​$72,765
​Deemed Ineligible - Not Formally Withdrawn
​N/A
​20
​Cooper City
COOPERC-R&M-01
​Stirling Road Milling and Resurfacing Project
​$1,036,960
​In Progress
Not Started
​21
​Dania Beach
DBEACH-R&M-01
​Resurface and Rebuild Base Project
​$297,905
​Not Started
Not Started
22
​Miramar
MIRAM-R&M-01
​City of Miramar Roadway resurfacing project I
​$1,995,001
​Executed - Project Underway​
​Bid Awarded
​23
​Coral Springs
CSPRINGS-R&M-01
​Coral Springs Alley Resurfacing Project
​$399,406​
​In Progress
Not Started
24

North Lauderdale​
NRTHLAUD-R&M-08
​Silver Lakes Drainage Improvements Project
​$1,440,093
​Not Started
Not Started
​25
​Margate
MARG-R&M-02
​Paradise Gardens Sidewalk and Valley Gutters Project
​$293,350
​​Not Started​
Not Started
​26
Weston​
WESTON-R&M-01
​Drainage improvements in neighborhood along Sailboat Circle
​$542,667.55*
​Executed - Project Underway
​Pending Solicitation
​27
Fort Lauderdale​
​FTLAUD-R&M-01
Fort Lauderdale Priority Sidewalk Maintenance
​$1,252,300
Deemed Ineligible - Not Formally Withdrawn
​N/A
28
​Margate
​MARG-R&M-01
​Margate Boulevard Bridge Repair Project
​$176,064
​Not Started
Not Started
​29
​Lighthouse Point
LHPOINT-R&M-02
​Sample Road Bridge Replacement Project
​$1,051,247
​Not Started
Not Started
30
​North Lauderdale
NRTHLAUD-R&M-06
​North Lauderdale Sidewalk and Curb Ramp Replacements/Repairs Project
​$2,914,575
​Not Started
Not Started
​31
​Sunrise
​SUNRISE-R&M-03
​Sunrise Milling and resurfacing of roadways Zone 1, Phase I
​$852,796
​Not Started
Not Started
​32

​Pembroke Pines
PBRKPINES-R&M-01
​Pembroke Pines Resurfacing and ADA Improvements Project
​$483,380
​Not Started
Not Started
​33
​Weston

​WESTON-R&M-02
​Bike lanes Pavement Marking Refurbishment
​$191,834
​Executed - Project Underway​
​Pending Solicitation
​34
​Fort Lauderdale
FTLAUD-R&M-03
​Finger Isles Asphalt Repair Project 
​$522,757
​Not Started
Not Started
​35
​Margate
​MARG-R&M-03
​City of Margate Roadway Resurfacing Project
​$1,053,184
​Not Started​
Not Started
​36
​Wilton Manors
WMANORS-R&M-01
​Milling, paving, and resurfacing throughout Wilton Manors Zone 1
​$1,334,667
Executed - Project Underway
Not Started
​37
​Wilton Manors
​WMANORS-R&M-03
​Milling, paving, and resurfacing throughout Wilton Manors Zone 2
​$1,425,600
Executed - Project Underway
Not Started
​38
​Wilton Manors
WMANORS-R&M-02
​Milling, paving, and resurfacing throughout Wilton Manors Zone 4
​$1,651,467
​Executed - project Underway
Not Started
​39
​Sunrise
​SUNRISE-R&M-06
​Sunrise Milling and resurfacing of roadways Zone 11, Phase I
​$1,853,260
​Not Started
Not Started
40
​Lauderdale Lakes
LLAKES-R&M-01
​Sidewalk Replacement and Repair Project
​$400,000
​Not Started
Not Started
​R&M

​Oakland Park
​OAKL-2020-003


​$510,510
​Not Started
​Not Started
R&M​

​Coral Springs
​CORA-2020-002


​$1,712,581.76
​Not Started
​Not Started
​R&M

​Hallandale Beach
​HALL-2020-002


​$162,978.55
​Not Started
​Not Started
​R&M

​North Lauderdale
​NLAU-2020-002


​$1,646,365.13
​Not Started
​Not Started
​R&M

​Lauderdale Lakes
​LLAK-2020-002


​$2,000,000
​Not Started
​Not Started
​R&M

​Margate
​MARG-2020-004


​$123,599.29
​Not Started
​​Not Started

Notes:

  • ​Projects were ranked in accordance to Section IV.A. of of the Second Amendment to the Transportation System Surtax Interlocal Agreement
  • ​Information provided as of November 2022
  • Projects #C3-1 to C3-8 are Cycle 3 MPO MCP Funding Recommendations pursuant to Section IV.B.1 of the Second Amendment to the Transportation System Surtax Interlocal Agreement
  • PFA Status​
    • ​Not Started: Municipality has not submitted a completed document packaged as established by Surtax Legal Counsel guidelines​
    • ​In Progress: Surtax Legal Counsel Team has received all required information and project documentation is under review. May require additional municipal submissions and actions.
    • Executed – Project Underway: Agreements have been finalized and projects’ current phases are in progress. 
  • Solicitation Status:
    • Bid Awarded: Municipality selected winning bid 
    • ​Bids Under Evaluation: Bidding window closed, and municipality is reviewing bids
    • Open Bid: Municipality has an open bid 
    • Closed Bid: Municipality has closed bidding
    • Pending Solicitation- Municipality will be posting solicitation soon 
    • Continuous Services- Municipality received approval from County to utilize an existing agreement compliant with surtax terms and conditions​

*Amounts reflect revised funding included in executed Project Funding Agreements.

For more detailed information on municipal Rehabilitation and Maintenance projects, click HE​RE.​​​



​​