​​​Segment III - Port Everglades Sand Byp​ass


The Port Everglades Sand Bypass project will completed through four phases of work: dredging, north jetty enhancement, artificial reef mitigation, and rubble removal. Dredging work has been awarded to Great Lakes Dredge and Dock with work to begin September 2024. Completion of the Project in total is estimated by the end of 2025.

A public webinar via Zoom will be hosted on Thursday, June 6th at 7pm est. Please use the following link to access: bit.ly/SandBypass (passcode 242284).

Further Info

Sand Bypass Industry Day.pdf ​

Beach webinar FAQ_Sand Bypass.pdf 

Background

The Sand Bypass Project exemplifies a long-term strategy for regional resilience in Southeast Florida, with substantial physical, economic, and environmental benefits to the Broward County Federal Shore Protection Project and Port Everglades Federal Navigation Channel.

The Sand Bypass Project will aid in serving as a supplemental sand source for the Broward County Segment III Shore Protection Project, which will provide for an economical, local source of sand in a county where local sources necessary for continued beach restoration and maintenance are nearly depleted.

Benefits

Implementation of the proposed Sand Bypass Project will: 

  • Increase the resilience of critical natural resources and existing infrastructure.

  • Reduce the impacts of Port Everglades to the shorelines south of the inlet.

  • Provide a sustainable beach compatible sand source for the highly erosional shorelines south of the inlet -- Segment III of the Broward County Federal Shore Protection Project, about 50% of sand needs.

  • Fortify and sustain storm protection for critical infrastructure and valuable property including the US Coast Guard Station, port facilities and over $345 million in property.

  • Reduce shoaling in the Federal navigation channel.

  • Preserve habitat and nesting areas for three endangered and four threatened species in one of the most highly developed urban areas in the state. 

  • Maintain opportunity for public outdoor recreation at Dr. Von D. Mizell-Eula Johnson State Park, serving over half a million residents and visitors annually. 

  • Provide the most environmentally sensitive approach to beach management in an area of rich coastal and nearshore reef resources. ​

Status

Construction is anticipated to begin the fall of 2024 and complete the end of 2025.​

If you have any questions about the Sand Bypass Project please contact Jacob Rice at jrice@broward.org